Drawing Approvals

Approvals

Application for approval of drawings in respect of newly established Master Unit sub-stations, switching stations, Master Receiving stations, Transmission Lines, Inter linking lines and UG cable laying of supplier installation and IPPs, Co-Gen, CPPs and MSB of 24 meters of height & above shall be submitted to the Chief Electrical Inspector to Govt. (CEIG), Bangalore and consumer installations of LT, HT, MSB of 15m and above & DG set installation shall be submitted to the Jurisdictional offices of Electrical Inspectorate as per the Delegation of powers (DOP) (To view Delegation Of Powers click here) with all the relevant drawings and details as listed below for the particular category of installation.

1.Common Documents

  • Application in Form-1 duly signed by the applicant or his GPA holder (along with copy of relevant document such as JDA/GPA etc.); in case of supplier/licensee installations not below the rank of The Assistant Executive Engineer or its equivalent.
  • Prescribed drawing scrutiny fees paid challan or Receipt.
  • Copy of valid License of the Electrical Contractor, Supervisor and; Wireman permit copy Endorsed to concerned LEC
  • Affidavit-8 : Authorization of owner of the installation to the Licensed Electrical Contractor on Rs 20 /- Stamp paper
  • Form Z: estimate and agreement made with the Licensed electrical Contractor and consumer on Rs 200/- stamp paper
  • Copy of proof of property ownership/occupancy document.

2.EHT Installations

  • Copy of power sanction letter from licensee along with sketch and estimate.

3.HT Installations

  • Copy of power sanction letter from licensee along with sketch and estimate.

4.TC/DCW Installations

  • Copy of power sanction letter from licensee along with sketch and estimate
  • In case of layouts copy of layout sanction plan from competent authority.

5.Terminal Bay extension

  • Copy of power sanction letter from licensee along with sketch and estimate.

6.EHV/ HV Line/Cable Installations

  • NOC from Railways, NOC from national highway, PTCC approval, NOC from Air port authority etc. and ROW documents (if applicable)
  • Check survey report along with tower schedule for transmission and power evacuation lines & approved topo-map (for 33kV and above).

7.LT Loads

  • Approval copy & approved drawings of existing installation where additions/alterations of Installation is proposed.
  • In case applicant is not the owner, consent from the owner of the installation.

8.Temporary Installation

  • Temporary power sanction letter by ESCOMS.

9.DG Set Installations

  • In case applicant is not the owner, consent from the owner of the installation.
  • Approval copy of existing installation along with ESCOM RR No. (if applicable).

10.Solar Installations

  • Govt. Order for captive and third party sale, wheeling and banking. (if applicable)
  • KREDL Letter of Award. (if applicable).
  • Work intimation letter in Format 6 in case of SRTPV.
  • Power Purchase Agreement (PPA) and/or Supplemental Power Purchase Agreement. (if applicable).
  • KERC approval for PPA/Supplemental PPA (if applicable).
  • Regular Power evacuation approval by ESCOM/KPTCL (if applicable).
  • Approved Building plan/license approved by competent authority along with Structural stability certificates from registered structural engineer in case of Solar Roof Top PV systems..
  • Copy Land conversion approvals from competent authority (if applicable).

11.Thermal Power Plants

  • Govt. Order for setting up Thermal Power plant.
  • Govt. Order for captive/sale of energy/wheeling and banking..
  • Regular Power evacuation approval by ESCOM/KPTCL.

12.Wind Power Plants

  • Govt. Order/any supplemental order for transfer of allotment.
  • KREDL agreement copy along with KREDL approved topo-map.
  • Copy Land conversion approvals from competent authority.
  • Regular Power evacuation approval by ESCOM/KPTCL.
  • Valid National Institute of Wind Energy Technology (NIWE) certificate for make & capacity of WTG.

13.Hydel/Mini Hydel Power Plants

  • Govt. Order for setting up Hydel Powe Plant..
  • Govt. Order for captive/sale of energy/wheeling and banking..
  • Regular Power evacuation approval by ESCOM/KPTCL.

14.Biomass Power Plants

  • Govt. Order for setting up Bio-mass power plant.
  • Govt. Order for captive/sale of energy/wheeling and banking.
  • Regular Power evacuation approval by ESCOM/KPTCL.

15.Gas Based Power Plants

  • Govt. Order for setting up Gas based power plant.
  • Govt. Order for captive/sale of energy/wheeling and banking..
  • Regular Power evacuation approval by ESCOM/KPTCL.

16.MSB Installations

  1. Copy of power sanction letter from licensee along with sketch and estimate.
  2. Copy of valid building sanction plan approved by the competent authority (in case of new building).

Note: Drawings shall be

    • Single Line Diagram of electrical installation showing all details from starting point to end point of the entire installation (For additions or alterations existing and proposed scheme shall be legibly marked)
    • Key plan or Site plan showing the location of transformer, Generator, Electrical Room, Panels, motors, etc.
    • Physical Layout/Plan: The Physical layout of the installation should show the location of all the equipments in relations to the location of switchboards and distribution boards. The clearance around the switchboards, distribution boards and main panels shall be indicated legibly.
    • Elevation in sections showing overhead clearance, Horizontal, Vertical and sectional clearances with respect to equipments and ground.
    • Method of construction of Earth pits / Earth mat as per standards and method of cable laying.